Ram Jack installed 256 three-inch extra strong pin piles on this project, with an average depth of twenty-one feet. They used a SP 15 vibratory sonic side grip to complete eight cabins, with thirty-two piles per cabin, in just five weeks. Verification test piles were installed at eight locations to verify depth and capacities.
The site of this project is located in an area with large-scale landslide topography, which required the use of pin piles. Pin piles were chosen because they were the most economical solution, given the quantity, soil conditions, and capacities required by structural and geotechnical engineering.